Projects

Khujwana Projects
Metsimotlhabe Project
Khujwana Construction did build a 3-bedroom house with single garage in Metsimotlhabe and the project took 3 months up to the stage agreed with the customer.


Thamaga Project
We also built a 3-bedroom house with a single garage and a servant's quater in Thamaga, which took a duration of 3 months to complete.
Francistown Project
We also built a Bachelor Pad at Francistown, which took 2 months due to the nature of the land which we were building on, which demanded us to dig a little deeper to remove the clay soil.


Mmopane Project
A bachelor pad in Mmopane Block 1, which took a month because it was only brickwork , roofing plastering and door installations that the customers wanted
Ramotswa Project
We extended a house from 2 rooms to a 3-bedroom house in Ramotswa, which we had to make a renovated floor plan for the new house. The total duration of this project was 3 months

Duration of Works
Description | Weeks/ Days |
|---|---|
Slab Level | 2 Weeks |
Brick Work | 2 Weeks |
Reinforcements | 2 Weeks |
Roofing | 5 Days |
Waterproofing | 3 Days |
Carpentry and Joinery Fittings | 6 Days |
Ceiling | 6 Days |
Doors and Locks | 2 Days |
Metal Works Doors and Window Frames | 4 Days |
Plastering and Screeding | 6 Days |
Tiling Floor and Wall | 1 Week |
Electrical Works | 1 Week |
Tiling Floor and Wall | 1 Week |
Plumbing and Drainage | 2 Weeks |
Glazing | 5 Days |
Painting | 3 Days |
Finish Rubble Collection | 3 Days |