Since 2011

Projects

Khujwana Projects

Metsimotlhabe (Click here to open)

Metsimotlhabe Project

Khujwana Construction did build a 3-bedroom house with single garage in Metsimotlhabe and the project took 3 months up to the stage agreed with the customer.

Metsimotlhabe

Thamaga (Click here to open)

Thamaga

Thamaga Project

We also built a 3-bedroom house with a single garage and a servant's quater in Thamaga, which took a duration of 3 months to complete.

Francistown (Click here to open)

Francistown Project

We also built a Bachelor Pad at Francistown, which took 2 months due to the nature of the land which we were building on, which demanded us to dig a little deeper to remove the clay soil.

Francistown

Mmopane (Click here to open)

Mmopane

Mmopane Project

A bachelor pad in Mmopane Block 1, which took a month because it was only brickwork , roofing plastering and door installations that the customers wanted

Ramotswa (Click here to open)

Ramotswa Project

We extended a house from 2 rooms to a 3-bedroom house in Ramotswa, which we had to make a renovated floor plan for the new house. The total duration of this project was 3 months

Ramotswa

Duration of Works

Description
Weeks/ Days

Slab Level

2 Weeks

Brick Work

2 Weeks

Reinforcements

2 Weeks

Roofing

5 Days

Waterproofing

3 Days

Carpentry and Joinery Fittings

6 Days

Ceiling

6 Days

Doors and Locks

2 Days

Metal Works Doors and Window Frames

4 Days

Plastering and Screeding

6 Days

Tiling Floor and Wall

1 Week

Electrical Works

1 Week

Tiling Floor and Wall

1 Week

Plumbing and Drainage

2 Weeks

Glazing

5 Days

Painting

3 Days

Finish Rubble Collection

3 Days